ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA GIL T033501C CL WARNER RD: RECKER RD - POWER RD VK1P IMPROVE ROADWAY CHRIS RODRIGUEZ
602-617-9560
3/28/2025 Lee Makler
602-712-8579
Current Program Budget $10,325,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-03-20 A
Stage 3 - 60% 2024-01-25 A
Stage 4 - 95% 2024-08-09
EPG Clearance 2024-06-06 A
RW Clearance 2025-04-08
URR Clearance 2025-02-25
Stage 5 - 100% 2025-04-08
Advertise 2025-03-29
Bids Opening 2025-05-17




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation