RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
69 YV 280.0 F028801C NW SR69 @ SR169 VG1P ROUNDABOUT ANGELA GALIETTI
602-712-7551
11/14/2024 Lee Makler
602-712-8579
Current Program Budget $8,532,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-08-30 A
Kickoff 2022-11-18 A
Stage 2 - 30% 2023-06-09 A
Stage 3 - 60% 2023-09-20 A
Stage 4 - 95% 2024-09-03 A
EPG Clearance 2024-08-22 A
RW Clearance 2024-10-16 A
URR Clearance 2024-10-23 A
Stage 5 - 100% 2024-10-23 A
Advertise 2024-11-14
Bids Opening 2025-01-23