RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 MA 122.0 F048601D CL JACKRABBIT TRAIL TI VF1P RECONSTRUCT TRAFFIC INTERCHANGE OLIVIER MIRZA
602-712-4032
Design Lee Makler
602-712-8579
Current Program Budget $6,500,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 3 - 60% 2025-09-26
Stage 4 - 95% 2025-09-27
EPG Clearance 2024-07-09 A
RW Clearance 2025-12-06
URR Clearance 2025-08-23
Stage 5 - 100% 2025-12-06
Advertise 2026-01-10
Bids Opening 2026-02-21