ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-09-01 A
Kickoff 2022-09-08 A
Stage 3 - 60% 2023-01-03 A
Stage 4 - 95% 2023-04-05 A
EPG Clearance 2023-04-28 A
RW Clearance 2023-04-28 A
URR Clearance 2023-04-25 A
Stage 5 - 100% 2023-05-25 A
Advertise 2023-06-08 A
Bids Opening 2023-08-18 A




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation