Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-03-14 A |
Kickoff | 2022-04-12 A |
Stage 2 - 30% | 2022-05-06 A |
Stage 3 - 60% | 2022-08-15 A |
Stage 4 - 95% | 2023-07-28 A |
EPG Clearance | 2023-06-22 A |
RW Clearance | 2025-03-29 |
URR Clearance | 2025-03-29 |
Stage 5 - 100% | 2025-03-29 |
Advertise | 2025-05-17 |
Bids Opening | 2025-05-17 |
|