Active Project List |
| Return to Project listing | Print this page |
| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2022-03-14 A |
| Kickoff | 2022-04-12 A |
| Stage 2 - 30% | 2022-05-06 A |
| Stage 3 - 60% | 2022-08-15 A |
| Stage 4 - 95% | 2023-07-28 A |
| EPG Clearance | 2023-06-22 A |
| RW Clearance | 2025-03-29 |
| URR Clearance | 2025-03-29 |
| Stage 5 - 100% | 2025-03-29 |
| Advertise | 2025-05-17 |
| Bids Opening | 2025-05-17 |
| |