RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 NA NNA T063301C NE SILVER CREEK DR & SILVER LAKE BLV TS1Q CONSTRUCT BRIDGE SAL SALAHUDDIN
602-712-7156
Design Lee Makler
602-712-8579
Current Program Budget $860,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-05-21
Kickoff 2025-05-03
Stage 2 - 30% 2025-05-21
Stage 3 - 60% 2025-05-22
Stage 4 - 95% 2025-06-12
EPG Clearance 2025-05-22
RW Clearance 2025-06-12
URR Clearance 2025-06-20
Stage 5 - 100% 2025-07-03
Advertise 2025-08-19
Bids Opening 2025-08-21