Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 NA NNA T063301C NE SILVER CREEK DR & SILVER LAKE BLV TS1Q REPLACE BRIDGE SAL SALAHUDDIN
602-712-7156
11/20/2026 Lee Makler
602-712-8579
Current Program Budget $860,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-05-30
Kickoff 2025-06-12
Stage 2 - 30% 2025-12-06
Stage 3 - 60% 2026-02-28
Stage 4 - 95% 2026-06-09
EPG Clearance 2026-04-24
RW Clearance 2026-07-24
URR Clearance 2026-07-24
Stage 5 - 100% 2026-08-22
Advertise 2026-11-21
Bids Opening 2027-01-23