Milestone Name Date  ("A" denotes actual finish)
NTP 2021-12-20 A
Kickoff 2021-08-25 A
Stage 2 - 30% 2021-08-25 A
Stage 3 - 60% 2022-05-06 A
Stage 4 - 95% 2022-09-09 A
EPG Clearance 2022-03-22 A
RW Clearance 2022-12-01 A
URR Clearance 2022-11-08 A
Stage 5 - 100% 2023-03-16 A
Advertise 2023-03-17 A
Bids Opening 2023-05-31 A