RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
17 CN 322.8 F075101C NC WILLARD SPRINGS WILDLIFE OVERPASS TM1Q WILDLIFE OVERPASS & GAME FENCING JUDAH CAIN
602-712-4493
11/29/2024 Lee Makler
602-712-8579
Current Program Budget $25,493,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 4 - 95% 2024-11-16
EPG Clearance 2024-09-17 A
RW Clearance 2024-10-04 A
URR Clearance 2024-09-20 A
Stage 5 - 100% 2024-11-18
Advertise 2024-11-30
Bids Opening 2025-02-22