Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-02-17 A |
Kickoff | 2023-02-17 A |
Stage 4 - 95% | 2023-11-03 A |
EPG Clearance | 2024-01-22 A |
RW Clearance | 2022-03-15 A |
URR Clearance | 2024-02-07 A |
Stage 5 - 100% | 2024-02-09 A |
Advertise | 2024-03-01 A |
Bids Opening | 2024-04-19 |
|