RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 AP 351.0 F031901C NE ALLENTOWN TI UP SZ1O REPLACE BRIDGE KIRSTIN HUSTON
602-712-8618
10/11/2024 Phil Schaffer
602 712-6845
Current Program Budget $13,000,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2020-07-27 A
Kickoff 2020-07-27 A
Stage 2 - 30% 2022-02-18 A
Stage 3 - 60% 2022-07-06 A
Stage 4 - 95% 2022-11-14 A
EPG Clearance 2022-08-05 A
RW Clearance 2022-11-18 A
URR Clearance 2022-11-10 A
Stage 5 - 100% 2024-08-31
Advertise 2024-10-12
Bids Opening 2024-12-21