RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA TOL T061901C CL VAN BUREN @ 96TH AVE, TOLLESON SY1Q CONSTRUCT PEDESTRIAN BRIDGE WESLEY SCATENA
602-712-8555
TBD Lee Makler
602-712-8579
Current Program Budget $3,712,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-03-01
Stage 2 - 30% 2025-03-19
Stage 3 - 60% 2025-03-20
Stage 4 - 95% 2025-04-10
EPG Clearance 2025-03-20
RW Clearance 2025-04-10
URR Clearance 2025-04-18
Stage 5 - 100% 2025-05-01
Advertise 2025-06-17
Bids Opening 2025-06-19