![]() |
Active Project List |
| Return to Project listing | Print this page |
| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2024-10-30 A |
| Kickoff | 2024-11-13 A |
| Stage 3 - 60% | 2025-01-31 A |
| Stage 4 - 95% | 2025-05-27 A |
| EPG Clearance | 2025-05-27 A |
| RW Clearance | 2025-04-30 A |
| URR Clearance | 2025-05-30 A |
| Stage 5 - 100% | 2025-06-11 A |
| Advertise | 2025-06-13 A |
| Bids Opening | 2025-10-17 A |
| |
| Arizona Department of Transportation |