Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-10-30 A |
Kickoff | 2024-11-13 A |
Stage 3 - 60% | 2025-01-25 |
Stage 4 - 95% | 2025-04-18 |
EPG Clearance | 2025-04-18 |
RW Clearance | 2025-05-08 |
URR Clearance | 2025-05-22 |
Stage 5 - 100% | 2025-05-22 |
Advertise | 2025-06-11 |
Bids Opening | 2025-10-07 |
|
Arizona Department of Transportation |