Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2020-04-13 A |
Kickoff | 2020-05-27 A |
Stage 3 - 60% | 2022-02-11 A |
Stage 4 - 95% | 2022-07-27 A |
EPG Clearance | 2022-03-14 A |
RW Clearance | 2022-04-15 A |
URR Clearance | 2022-10-13 A |
Stage 5 - 100% | 2022-10-21 A |
Advertise | 2022-11-10 A |
Bids Opening | 2023-01-20 A |
|
Arizona Department of Transportation |