| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2024-06-17 A |
| Kickoff | 2024-07-01 A |
| Stage 2 - 30% | 2025-03-14 A |
| Stage 3 - 60% | 2025-03-14 A |
| Stage 4 - 95% | 2025-07-16 A |
| EPG Clearance | 2025-07-16 A |
| RW Clearance | 2025-06-30 A |
| URR Clearance | 2025-07-15 A |
| Stage 5 - 100% | 2025-08-05 A |
| Advertise | 2025-09-03 A |
| Bids Opening | 2025-11-22 |
| |