Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Stage 2 - 30% | 2021-01-29 A |
Stage 3 - 60% | 2021-03-26 A |
Stage 4 - 95% | 2021-07-09 A |
EPG Clearance | 2021-07-02 A |
RW Clearance | 2021-07-19 A |
URR Clearance | 2021-07-15 A |
Stage 5 - 100% | 2024-05-25 |
Advertise | 2024-06-11 |
|