RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 PM 291.9 F042601C SC AMOLE RR OP EB/WB , AMOLE TIOP SH1O BRIDGE REHABILITATION JUDAH CAIN
602-712-4493
11/1/2024 Lee Makler
602-712-8579
Current Program Budget $9,318,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-03-07 A
Kickoff 2022-04-26 A
Stage 2 - 30% 2022-07-27 A
Stage 3 - 60% 2023-01-13 A
Stage 4 - 95% 2023-12-19 A
EPG Clearance 2023-09-12 A
RW Clearance 2024-01-09 A
URR Clearance 2024-01-04 A
Stage 5 - 100% 2024-09-14
Advertise 2024-11-02
Bids Opening 2025-01-18