Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-03-07 A |
Kickoff | 2022-04-26 A |
Stage 2 - 30% | 2022-07-27 A |
Stage 3 - 60% | 2023-01-13 A |
Stage 4 - 95% | 2023-12-19 A |
EPG Clearance | 2023-09-12 A |
RW Clearance | 2024-01-09 A |
URR Clearance | 2024-01-04 A |
Stage 5 - 100% | 2024-09-14 |
Advertise | 2024-11-02 |
Bids Opening | 2025-01-18 |
|