RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
60 MA 159.0 F027201C CL 35TH AVE / INDIAN SCHOOL RD INTER SE1O RECONSTRUCT TI OLIVIER MIRZA
602-712-4032
Design Lee Makler
602-712-8579
Current Program Budget $16,856,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 3 - 60% 2025-03-01
Stage 4 - 95% 2025-07-17
RW Clearance 2025-12-18
URR Clearance 2025-12-18
Stage 5 - 100% 2025-12-18
Advertise 2026-02-03
Bids Opening 2026-02-05