RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 MO 3.6 F081701C NW TOPOCK PORT OF ENTRY SB1Q CONSTRUCT INSPECTION PIT CHRIS MOORE
602-712-2132
TBD Lee Makler
602-712-8579
Current Program Budget $2,400,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-04-22
Kickoff 2025-09-27
Stage 2 - 30% 2025-12-02
Stage 3 - 60% 2026-04-25
Stage 4 - 95% 2026-09-05
EPG Clearance 2026-06-09
RW Clearance 2026-09-07
URR Clearance 2026-09-15
Stage 5 - 100% 2026-12-05
Advertise 2027-01-21
Bids Opening 2027-01-23