ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 CN 190.0 F077201C NC RIORDAN BNSF RAILROAD OVERPASS EB RX1Q REPLACE BRIDGE ARASH GHAZANFARI
602-712-8336
9/16/2026 Lee Makler
602-712-8579
Current Program Budget $45,000,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-04-24 A
Stage 2 - 30% 2025-10-09
Stage 3 - 60% 2026-01-01
Stage 4 - 95% 2026-03-12
EPG Clearance 2026-02-12
RW Clearance 2026-04-09
URR Clearance 2026-04-09
Stage 5 - 100% 2026-04-09
Advertise 2026-09-17
Bids Opening 2026-11-27




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation