RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 GI GGI T061301C SE RUSSELL ROAD; MP 3.5 - MP 5.2 RI1Q RECONSTRUCT ROADWAY TRICIA BROWN
602-712-7046
Design Lee Makler
602-712-8579
Current Program Budget $1,041,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-07-18
Kickoff 2024-07-18
Stage 2 - 30% 2024-07-24
Stage 3 - 60% 2024-08-28
Stage 4 - 95% 2024-09-11
EPG Clearance 2024-09-11
RW Clearance 2024-07-24
URR Clearance 2024-07-20
Stage 5 - 100% 2024-08-07
Advertise 2024-07-18
Bids Opening 2024-07-19