RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 LA 17.0 F076901C SW WEST QUARTZSITE TI & FRONTAGE RD RE1Q INTERCHANGE & FRONTAGE RD IMPROVEMENTS PEDRAM SHAFIEIAN
602-712-8166
Design Lee Makler
602-712-8579
Current Program Budget $3,400,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-11-05
Kickoff 2024-11-16
Stage 2 - 30% 2025-04-11
Stage 3 - 60% 2025-09-19
Stage 4 - 95% 2026-02-06
EPG Clearance 2025-11-14
RW Clearance 2026-03-19
URR Clearance 2026-04-11
Stage 5 - 100% 2026-04-14
Advertise 2026-05-14
Bids Opening 2026-08-22