RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 LA 17.0 F076901C SW WEST QUARTZSITE TI & FRONTAGE RD RE1Q INTERCHANGE & FRONTAGE RD IMPROVEMENTS PEDRAM SHAFIEIAN
602-712-8166
9/25/2026 Lee Makler
602-712-8579
Current Program Budget $3,400,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-07-09 A
Stage 2 - 30% 2025-11-18
Stage 3 - 60% 2026-03-17
Stage 4 - 95% 2026-06-16
EPG Clearance 2026-04-21
RW Clearance 2026-08-18
URR Clearance 2026-07-14
Stage 5 - 100% 2026-08-25
Advertise 2026-09-25
Bids Opening 2026-12-19