RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
999 SW 0.0 F076301D XX STATEWIDE - ITS QI1Q ITS DEPLOYMENT SHAFIQUL ISLAM
602-712-6431
Design Lee Makler
602-712-8579
Current Program Budget $300,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-06-25
Stage 2 - 30% 2025-08-29
Stage 3 - 60% 2025-11-21
Stage 4 - 95% 2026-02-28
EPG Clearance 2026-05-07
RW Clearance 2026-02-28
URR Clearance 2026-02-28
Stage 5 - 100% 2026-04-10
Advertise 2026-06-23