RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA SUR T058801C CL WADDELL RD; LITCHFIELD RD - BULLA QD1Q CONDUIT, PULL BOXES & FIBER OPTIC CABLE TED SMITHWICK
602-228-5378
6/10/2025 Lee Makler
602-712-8579
Current Program Budget $543,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-09-03
Kickoff 2024-12-05
Stage 2 - 30% 2024-12-20
Stage 3 - 60% 2025-01-17
Stage 4 - 95% 2025-03-14
EPG Clearance 2025-03-14
RW Clearance 2025-03-21
URR Clearance 2025-03-22
Stage 5 - 100% 2025-04-04
Advertise 2025-06-10
Bids Opening 2025-06-11