ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA SUR T058801C CL WADDELL RD; LITCHFIELD RD - BULLA QD1Q CONDUIT, PULL BOXES & FIBER OPTIC CABLE TED SMITHWICK
602-228-5378
6/10/2025 Lee Makler
602-712-8579
Current Program Budget $543,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-01-21
Kickoff 2025-04-24
Stage 2 - 30% 2025-05-09
Stage 3 - 60% 2025-06-06
Stage 4 - 95% 2025-08-01
EPG Clearance 2025-08-01
RW Clearance 2025-08-08
URR Clearance 2025-08-09
Stage 5 - 100% 2025-08-22
Advertise 2025-10-28
Bids Opening 2025-10-29




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation