RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 MA 120.0 F074501C CL VERRADO WAY - 99TH AVE PS1Q CONVERT HPS TO LED LIGHTING JEFFREY DAVIDSON
602-712-8534
6/6/2025 Lee Makler
602-712-8579
Current Program Budget $3,000,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-01-07 A
Stage 4 - 95% 2025-04-21 A
EPG Clearance 2025-04-11 A
RW Clearance 2025-04-18 A
URR Clearance 2025-04-15 A
Stage 5 - 100% 2025-05-01
Advertise 2025-06-07