Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2018-09-05 A |
Stage 2 - 30% | 2019-05-30 A |
Stage 3 - 60% | 2020-06-11 A |
Stage 4 - 95% | 2020-12-21 A |
EPG Clearance | 2021-10-26 A |
RW Clearance | 2022-03-29 A |
URR Clearance | 2022-05-17 A |
Stage 5 - 100% | 2022-05-17 A |
Advertise | 2022-06-03 A |
Bids Opening | 2022-09-16 A |
|