RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40B CN 193.6 F075701C NC ALVAN CLARK WAY - N FANNING DR PJ1Q PAVEMENT REHABILITATION VIVIAN LI
602-712-8708
7/31/2026 Lee Makler
602-712-8579
Current Program Budget $19,310,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-09-27 A
Kickoff 2024-10-21 A
Stage 2 - 30% 2025-04-28 A
Stage 3 - 60% 2025-06-26 A
Stage 4 - 95% 2025-11-22
EPG Clearance 2025-11-22
RW Clearance 2025-11-24
URR Clearance 2025-12-02
Stage 5 - 100% 2026-02-28
Advertise 2026-08-01
Bids Opening 2026-08-05