Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2025-06-10 |
Kickoff | 2025-05-23 |
Stage 2 - 30% | 2025-06-10 |
Stage 3 - 60% | 2025-06-11 |
Stage 4 - 95% | 2025-07-02 |
EPG Clearance | 2025-06-11 |
RW Clearance | 2025-07-02 |
URR Clearance | 2025-07-10 |
Stage 5 - 100% | 2025-07-23 |
Advertise | 2025-09-06 |
Bids Opening | 2025-09-10 |
|