Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2018-11-30 |
Kickoff | 2018-12-11 |
Stage 2 - 30% | 2018-12-15 |
Stage 3 - 60% | 2019-01-30 |
Stage 4 - 95% | 2019-03-28 |
EPG Clearance | 2019-03-28 |
RW Clearance | 2019-04-04 |
URR Clearance | 2019-04-05 |
Stage 5 - 100% | 2019-04-18 |
Advertise | 2019-05-10 |
Bids Opening | 2019-05-11 |
|