Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
17 MA 194.0 H756301D CL I-10 SPLIT - 19TH AVE PG1J CONSTRUCT WIDENING BHARAT KANDEL
602-712-8736
10/7/2026 Lee Makler
602-712-8579
Current Program Budget $83,994,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2020-08-17 A
Kickoff 2020-08-18 A
Stage 3 - 60% 2021-09-23 A
Stage 4 - 95% 2021-11-23 A
RW Clearance 2022-04-30
URR Clearance 2022-04-30
Stage 5 - 100% 2022-05-28
Advertise 2026-10-07




For Project Resource Office information or questions: PRO Mailbox