Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2020-08-17 A |
Kickoff | 2020-08-18 A |
Stage 3 - 60% | 2021-09-23 A |
Stage 4 - 95% | 2021-11-23 A |
RW Clearance | 2022-04-30 |
URR Clearance | 2022-04-30 |
Stage 5 - 100% | 2022-05-28 |
Advertise | 2026-10-07 |
|