PG1J PRO Gantt Chart
ADOTNet : Home

Active Project List



Cutoff Date: 10/15/2018
0% = Task not started | 100% = Task completed

Activity Activity
Name
Planned
Start
Planned
Finish
Early/Actual
Start
Early/Actual
Finish
AUG 11 SEP 11 OCT 11 NOV 11 DEC 11 JAN 12 FEB 12 MAR 12 APR 12 MAY 12 JUN 12 JUL 12 AUG 12 SEP 12 OCT 12 NOV 12 DEC 12 JAN 13 FEB 13 MAR 13 APR 13 MAY 13 JUN 13 JUL 13 AUG 13 SEP 13 OCT 13 NOV 13 DEC 13 JAN 14 FEB 14 MAR 14 APR 14 MAY 14 JUN 14 JUL 14 AUG 14 SEP 14 OCT 14 NOV 14 DEC 14 JAN 15 FEB 15 MAR 15 APR 15 MAY 15 JUN 15 JUL 15 AUG 15 SEP 15
AN39XFA PE Federal Authorization (Obtained) 07/02/2018 07/02/2018 08/08/2011 08/08/2011
 
  u  
AN46XEP Environmental Clearance (Obtained) 07/02/2018 07/02/2018 06/24/2015 06/24/2015
 
  u  
AN39XPL Final PA Submittal 07/02/2018 07/02/2018 06/25/2015 09/16/2015
 
     
AN39XPL10 Initial PA Submitted 07/02/2018 07/02/2018 06/25/2015 06/25/2015
 
  u  
AN42XPL Stage II (30%) Submittal 07/02/2018 07/02/2018 09/16/2015 09/16/2015
 
  u  


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation