Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-08-21 A |
Kickoff | 2024-08-23 A |
Stage 3 - 60% | 2024-12-03 |
EPG Clearance | 2025-01-04 |
RW Clearance | 2025-01-18 |
URR Clearance | 2025-01-18 |
Stage 5 - 100% | 2025-01-14 |
Advertise | 2025-02-01 |
Bids Opening | 2025-03-15 |
|
Arizona Department of Transportation |