Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-08-21 A |
Kickoff | 2024-08-23 A |
Stage 3 - 60% | 2024-12-03 A |
EPG Clearance | 2024-12-24 A |
RW Clearance | 2025-01-03 A |
URR Clearance | 2025-01-17 A |
Stage 5 - 100% | 2025-02-22 |
Advertise | 2025-03-14 A |
Bids Opening | 2025-04-30 |
|