Active Project List |
| Return to Project listing | Print this page |
| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| Kickoff | 2024-07-25 A |
| Stage 2 - 30% | 2024-12-06 A |
| Stage 3 - 60% | 2024-12-20 A |
| Stage 4 - 95% | 2025-03-14 A |
| EPG Clearance | 2025-03-14 A |
| RW Clearance | 2025-03-14 A |
| URR Clearance | 2025-03-26 A |
| Stage 5 - 100% | 2025-04-11 A |
| Advertise | 2025-04-30 A |
| |