Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Kickoff | 2024-07-25 A |
Stage 2 - 30% | 2024-10-18 |
Stage 3 - 60% | 2024-12-14 |
Stage 4 - 95% | 2025-03-01 |
EPG Clearance | 2025-02-01 |
RW Clearance | 2025-02-11 |
URR Clearance | 2025-03-06 |
Stage 5 - 100% | 2025-04-19 |
Advertise | 2025-05-15 |
|
Arizona Department of Transportation |