ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
93 MO 27.6 F073601D NW US93 @ BONANZA DR OR1Q REMOVE/REPLACE DMS MADISON SHUGRUE
602-712-8895
TBD Lee Makler
602-712-8579
Current Program Budget   Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-02-19 A
Kickoff 2025-02-19 A
Stage 2 - 30% 2024-10-01
Stage 3 - 60% 2024-10-02
Stage 4 - 95% 2024-10-23
EPG Clearance 2024-10-02
RW Clearance 2024-10-23
URR Clearance 2025-04-29
Stage 5 - 100% 2025-04-29
Advertise 2025-06-13
Bids Opening 2025-06-17




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation