Current Program Budget   Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-02-19 A
Kickoff 2025-02-19 A
Stage 2 - 30% 2025-06-24 A
Stage 3 - 60% 2024-10-02
Stage 4 - 95% 2025-07-18
EPG Clearance 2025-07-18
RW Clearance 2025-06-30 A
URR Clearance 2025-07-29
Stage 5 - 100% 2025-07-29
Advertise 2025-09-12
Bids Opening 2025-09-16