Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-04-17 A |
Kickoff | 2023-06-08 A |
Stage 2 - 30% | 2023-06-20 A |
Stage 3 - 60% | 2024-02-06 A |
Stage 4 - 95% | 2024-06-21 A |
EPG Clearance | 2024-05-31 A |
RW Clearance | 2024-06-29 |
URR Clearance | 2024-06-11 A |
Stage 5 - 100% | 2024-07-27 |
Advertise | 2024-08-24 |
Bids Opening | 2024-10-19 |
|