RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 CH 383.0 F072801C SE SAN SIMON PORT OF ENTRY OI1Q REPLACE SCALE & CONSTRUCT INSPECTION PIT CHRIS MOORE
602-712-2132
TBD Lee Makler
602-712-8579
Current Program Budget $4,800,000 Program FY 28

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-12-02 A
Kickoff 2025-01-22 A
Stage 2 - 30% 2025-04-05
Stage 3 - 60% 2025-09-04
Stage 4 - 95% 2026-03-05
EPG Clearance 2025-10-30
RW Clearance 2026-04-15
URR Clearance 2026-05-05
Stage 5 - 100% 2026-05-14
Advertise 2026-06-13
Bids Opening 2026-06-16