Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-08-15
Kickoff 2024-08-21
Stage 3 - 60% 2025-01-08
Stage 4 - 95% 2025-04-16
EPG Clearance 2025-03-05
RW Clearance 2025-05-27
URR Clearance 2025-06-14
Stage 5 - 100% 2025-06-14
Advertise 2025-07-16
Bids Opening 2025-07-17