Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2021-06-24 A
Kickoff 2021-06-24 A
Stage 2 - 30% 2021-08-30 A
Stage 3 - 60% 2021-10-27 A
Stage 4 - 95% 2022-04-28 A
EPG Clearance 2022-04-28 A
RW Clearance 2022-05-04 A
URR Clearance 2022-05-20 A
Stage 5 - 100% 2022-05-20 A
Advertise 2023-03-15 A