RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 PN CSG T053001C SC THORNTON ROAD; SR 84 - PETERS RD NG1Q WIDEN ROADWAY CHINWE IWUCHUKWU
626-222-7982
1/7/2025 Lee Makler
602-712-8579
Current Program Budget $5,530,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 3 - 60% 2025-02-13
Stage 4 - 95% 2025-07-18
EPG Clearance 2025-07-18
RW Clearance 2025-07-18
URR Clearance 2025-07-26
Stage 5 - 100% 2025-10-30
Advertise 2025-12-18
Bids Opening 2025-12-20