Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2021-11-08 A |
Kickoff | 2021-12-16 A |
Stage 2 - 30% | 2022-08-26 A |
Stage 3 - 60% | 2024-09-20 A |
Stage 4 - 95% | 2024-12-21 |
EPG Clearance | 2024-09-04 A |
RW Clearance | 2025-04-16 |
URR Clearance | 2025-02-28 |
Stage 5 - 100% | 2025-03-25 |
Advertise | 2025-06-07 |
Bids Opening | 2025-08-30 |
|
Arizona Department of Transportation |