| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2021-05-25 A |
| Kickoff | 2021-05-25 A |
| Stage 3 - 60% | 2022-05-10 A |
| Stage 4 - 95% | 2023-03-06 A |
| EPG Clearance | 2022-10-18 A |
| RW Clearance | 2022-11-18 A |
| URR Clearance | 2022-04-01 A |
| Stage 5 - 100% | 2023-05-10 A |
| Advertise | 2023-05-17 A |
| Bids Opening | 2023-07-21 A |
| |