RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
89 YV 331.0 F055901C NW W ROAD 5 N - PAULDEN MQ1P CONSTRUCT RUMBLE STRIPS CHRIS MOORE
602-712-2132
5/24/2024 Lee Makler
602-712-8579
Current Program Budget $2,562,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-11-15 A
Stage 3 - 60% 2023-11-08 A
Stage 4 - 95% 2024-04-04 A
EPG Clearance 2024-01-23 A
RW Clearance 2024-03-07 A
URR Clearance 2024-03-22 A
Stage 5 - 100% 2024-04-24 A
Advertise 2024-05-25
Bids Opening 2024-08-17