Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2020-11-20 A
Kickoff 2021-01-27 A
Stage 2 - 30% 2021-10-18 A
Stage 3 - 60% 2022-02-11 A
Stage 4 - 95% 2022-06-06 A
EPG Clearance 2022-10-06 A
RW Clearance 2022-06-21 A
URR Clearance 2022-08-04 A
Stage 5 - 100% 2022-09-02 A
Advertise 2022-11-28 A
Bids Opening 2023-02-10 A
Award Date 2023-03-17 A