| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2022-11-29 A |
| Kickoff | 2022-12-15 A |
| Stage 2 - 30% | 2023-05-05 A |
| Stage 3 - 60% | 2024-01-02 A |
| Stage 4 - 95% | 2024-03-22 A |
| EPG Clearance | 2024-01-26 A |
| RW Clearance | 2024-05-14 A |
| URR Clearance | 2024-04-30 A |
| Stage 5 - 100% | 2024-05-17 A |
| Advertise | 2024-06-20 A |
| Bids Opening | 2024-09-20 A |
| |