RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
999 SW 0.0 M723201X XX VARIOUS LOCATIONS - ATMS TRAFFIC ML1Q PROCURE AND INTEGRATE SIGNAL SYSTEM ADAM MCGUIRE
602-712-8403
6/14/2024 Lee Makler
602-712-8579
Current Program Budget $900,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-01-12 A
Kickoff 2024-01-18 A
Stage 4 - 95% 2024-03-01 A
EPG Clearance 2023-12-05 A
RW Clearance 2024-03-07 A
URR Clearance 2024-04-16 A
Stage 5 - 100% 2024-03-29 A
Advertise 2024-06-15
Bids Opening 2024-08-24
Award Date 2024-09-05