RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 CH 302.9 F056401C SC SR 90 - SR 80, WB, WEST OF BENSO MJ1P CLIMBING LANE ANGELA GALIETTI
602-712-7551
6/24/2024 Lee Makler
602-712-8579
Current Program Budget $3,430,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-01-12 A
Kickoff 2023-01-19 A
Stage 2 - 30% 2023-03-28 A
Stage 3 - 60% 2023-07-14 A
Stage 4 - 95% 2024-03-28 A
EPG Clearance 2024-02-02 A
RW Clearance 2024-04-16 A
URR Clearance 2024-05-06 A
Stage 5 - 100% 2024-09-05
Advertise 2024-06-24 A