ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
101L MA 0.0 F047501D CL SR101L & I-10 SYSTEM INTERCHANGE MJ1O SYSTEM TI IMPROVEMENTS RASHIDUL HAQUE
602-712-7352
4/25/2025 Jeff Ross
602-712-8477
Current Program Budget $252,294,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2022-07-09 A
Stage 1 - 15% 2023-08-31 A
Stage 3 - 60% 2024-07-30
Stage 4 - 95% 2024-12-07
EPG Clearance 2023-10-31 A
URR Clearance 2025-02-01
Stage 5 - 100% 2025-02-26
Advertise 2025-04-26




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation