Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Kickoff | 2022-07-09 A |
Stage 1 - 15% | 2023-08-31 A |
Stage 3 - 60% | 2024-08-06 A |
Stage 4 - 95% | 2024-12-21 |
EPG Clearance | 2023-10-31 A |
RW Clearance | 2025-01-08 |
URR Clearance | 2025-02-01 |
Stage 5 - 100% | 2025-03-04 |
Advertise | 2025-04-26 |
|