Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2019-09-17 A |
Kickoff | 2019-10-08 A |
Stage 2 - 30% | 2020-05-21 |
Stage 3 - 60% | 2020-09-17 |
Stage 4 - 95% | 2021-01-14 |
EPG Clearance | 2021-02-25 |
RW Clearance | 2021-03-04 |
URR Clearance | 2021-03-04 |
Stage 5 - 100% | 2021-03-24 |
Advertise | 2021-05-05 |
Award Date | 2021-08-11 |
|