Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
17 MA 203.0 F016601C CL INDIAN SCHOOL RD TI MD1O CONSTRUCT TI TRENT KELSO
602-712-6685
Hold Lee Makler
602-712-8579
Current Program Budget $67,059,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2019-09-17 A
Kickoff 2019-10-08 A
Stage 2 - 30% 2020-05-21
Stage 3 - 60% 2020-09-17
Stage 4 - 95% 2021-01-14
EPG Clearance 2021-02-25
RW Clearance 2021-03-04
URR Clearance 2021-03-04
Stage 5 - 100% 2021-03-24
Advertise 2021-05-05
Award Date 2021-08-11