RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 PN MAR T045801C CL PEDESTRIAN BRIDGE OVER THE UNION MA1Q CONSTRUCT PEDESTRIAN BRIDGE REHNUMA RAHMAN
602-712-7342
7/31/2024 Lee Makler
602-712-8579
Current Program Budget $2,300,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-11-07 A
Stage 4 - 95% 2024-05-16
EPG Clearance 2024-05-16
RW Clearance 2024-04-18 A
URR Clearance 2024-05-18
Stage 5 - 100% 2024-06-15
Advertise 2024-08-01
Bids Opening 2024-09-28