ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 PN MAR T045801C CL PEDESTRIAN BRIDGE OVER THE UNION MA1Q CONSTRUCT PEDESTRIAN BRIDGE REHNUMA RAHMAN
602-712-7342
8/14/2024 Lee Makler
602-712-8579
Current Program Budget $2,300,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-11-07 A
Stage 4 - 95% 2024-05-15 A
EPG Clearance 2024-05-15 A
RW Clearance 2024-04-18 A
URR Clearance 2024-06-20 A
Stage 5 - 100% 2024-07-17
Advertise 2024-08-14
Bids Opening 2024-10-19




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation