Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2020-05-26 A |
Kickoff | 2020-05-07 A |
Stage 2 - 30% | 2020-07-17 A |
Stage 3 - 60% | 2021-08-31 A |
Stage 4 - 95% | 2022-01-18 A |
EPG Clearance | 2023-10-30 A |
RW Clearance | 2025-01-09 |
URR Clearance | 2025-01-25 |
Stage 5 - 100% | 2025-07-02 |
Advertise | 2025-09-27 |
|