| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2020-05-26 A |
| Kickoff | 2020-05-07 A |
| Stage 2 - 30% | 2020-07-17 A |
| Stage 3 - 60% | 2021-08-31 A |
| Stage 4 - 95% | 2022-01-18 A |
| EPG Clearance | 2023-10-30 A |
| RW Clearance | 2025-01-23 A |
| URR Clearance | 2025-08-20 A |
| Stage 5 - 100% | 2025-08-16 |
| Advertise | 2025-09-26 A |
| |