ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 PN 177.0 F033601C SC GAS LINE RD - DIRK LAY ROAD LR1P WIDEN ROADWAY TRENT KELSO
602-712-6685
3/26/2025 Lee Makler
602-712-8579
Current Program Budget $160,593,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-03-03 A
Kickoff 2022-07-11 A
Stage 2 - 30% 2022-10-31 A
Stage 3 - 60% 2023-08-25 A
Stage 4 - 95% 2024-04-26 A
EPG Clearance 2024-12-03
RW Clearance 2025-02-19
URR Clearance 2025-02-25
Stage 5 - 100% 2025-02-08
Advertise 2025-03-26
Bids Opening 2025-06-04




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation