RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 PN 173.8 F033601D SC NORTH OF NELSON RD - DIRK LAY ROA LR1P WIDENING TRENT KELSO
602-712-6685
12/13/2024 Lee Makler
602-712-8579
Current Program Budget $10,070,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-03-03 A
Kickoff 2022-07-11 A
Stage 2 - 30% 2022-10-31 A
Stage 3 - 60% 2023-08-25 A
Stage 4 - 95% 2024-04-27
EPG Clearance 2024-05-17
RW Clearance 2024-10-11
URR Clearance 2024-11-15
Stage 5 - 100% 2024-08-31
Advertise 2024-12-14
Bids Opening 2025-02-22