Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-03-03 A |
Kickoff | 2022-07-11 A |
Stage 2 - 30% | 2022-10-31 A |
Stage 3 - 60% | 2023-08-25 A |
Stage 4 - 95% | 2024-04-26 A |
EPG Clearance | 2025-01-21 A |
RW Clearance | 2025-01-10 A |
URR Clearance | 2025-01-16 A |
Stage 5 - 100% | 2025-04-09 |
Advertise | 2025-05-01 |
Bids Opening | 2025-08-23 |
|