RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 CH CCH T049701C SC DAVIS RD; MP5 & MP13 LM1Q PAVEMENT & DRAINAGE REHABILITATION ARASH GHAZANFARI
602-712-8336
3/11/2024 Lee Makler
602-712-8579
Current Program Budget $3,068,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-06-29
Stage 4 - 95% 2024-08-01
EPG Clearance 2024-07-18
RW Clearance 2024-08-08
URR Clearance 2024-08-15
Stage 5 - 100% 2024-08-31
Advertise 2024-11-09
Bids Opening 2024-11-12